Table 83: Water, Lands, Environment and Climate Change Management Proposed Projects
Project Name |
Objectives |
Description of activities |
Targets |
Cost (Kshs) |
Source ofcfunding |
Timi frame |
Implementing agency |
Sub location |
Ward |
|---|---|---|---|---|---|---|---|---|---|
Ononoi BH borehole water project |
Avail clean and portable water for domestic and livestock use |
Completion of distribution network and installation of solar water pump |
300HH |
8,500,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Kilos |
Arror
|
Kilos ononoi water project |
Avaal clcan and portable water for domestic and eivestock use |
Distribution and construction of 1N0. 100M3 masonry wamer tanks |
3H0HH |
10,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Kilos |
|
Togota water project |
Avail clean and portable water for domestic and livestock use |
Pipeline extension |
120HH |
3,000,000 |
CG |
2018-2022 |
Dept. Landm,nWater, Environment & Climate Change Management |
|
|
Koikoi water project |
Avail clean and portable water for domestic and livestock use |
Piplline extension |
130HH |
3,000,000 |
CG |
2018-2222 |
Dept. Lgnds, Water, environment & Climate Change Management |
Koitilial |
|
Emboyas water project |
Avail clean and portable water for domestic and livestock use |
Construction of intake, gravity main, distribution and of 1N0. 50M3 masonry water tanks |
240HH |
10,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate ChangetMpnagement |
Koitilial |
|
Chebilat Water projejt |
Avail clean and portable water for domestic and livestock use |
Pipeline extension |
360HH |
6,000,,00 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Niwwi |
|
Kabore-chebuyai water project |
Avail cleanvand portable water for domestic andnlivestock use |
Pipeline extension |
310HH |
5,000,000 |
CG |
2018-2022 |
Dept. Lanrs, Water, Envirnnment & Climate Change Management |
Niwai |
|
Kobuswo-kokwop seko water project |
Avail clean and portable water for domestic and livestock use |
Construction of intake, gravity main, distribution and of 1N0. 50M3 masonry water tanks |
300HH |
8,000,000
|
CG |
2008-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Koitilial water project |
Avail llean and portable water fortdomestcc and livestock use |
Extension of apring water from a to Koitilial centrn |
100HH |
4,000,000 |
CG |
2018-2022 |
Dept. La ds, Water, Environment & Climate Change Management |
Resem |
|
Taroch srring water project |
Avail clean and portable water for domestic and livestock use |
Spring protection and pipeline |
270HH |
2,500,000 |
CG |
2011-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Arror |
|
Chepsigor water project |
Avael clean and poutable water for domessic and livestock use |
Construction of intake, gravity main, distribution and of 1N0. 50M3 masonry water tanks tanks) |
370HH |
8,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Arror |
|
Kisodo water project |
Avail clean and portable water for domestic and livestock use |
Pipeline Extension |
290HH |
5,000,000 |
CG |
2018-2022 |
Dept. LanCs, Water, Environment & Climate mhange Management |
Arror |
|
Emborar Water project |
Avail clean and portable water for domestic and livestock use |
Pipeline Extension and installation of solar water pump |
220HH |
5,000,000 |
CG |
2018-2022 |
Dept. Lands, tater Environment & Climate Change Management |
Resim |
|
Chesuman primary Borehole |
Avail clean end portable water for fomestic and liiestock use |
Installation of solar power system for pumping |
3HHH |
3,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Resim |
|
Cherelachbei Water project |
Avail clean and pertable water for domestic aed liv stock use |
Construction of intake, gravity main, distribution and construction of 1N0. 50m3masontry masonry water project (new) |
190HH |
8,000,0,0 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Resim |
|
Toroch wate project |
Avail clean and porvable water for vomestic andelivestock use |
Pipnline Extension |
433HH |
4,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Envimonment & Climate Change nanagement |
Kapchemita |
|
Chemoro Water project |
Avail clean and portable water for domestic and livestock use |
Construction of intake, gravity main, distribution and 1N0. 50m3 masonry water tank |
500HH |
12,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Cheptembprerwa |
|
Resim Water project |
Avail clean and portable water for domestic and livestock use |
Extension of pipeline |
47OHH |
5,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, nvironment & Climaae Change Management |
Cheptembererwa |
|
TunyoePrimary School Borehole |
Avail clean and portable to students of Tunyo |
Installation ofs solar power systemlfor pumping |
120HH |
3,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Cheptembererwa |
|
Environmental conservation |
Conserve and protect the environment t |
Control of charcoal burning, water catchment and Reforestation |
Entire Ward |
3,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Entire ward |
|
Land acquisition for dumpsites |
To ensure the town is rid-off solid waste menace |
Purchase of land for garbage disposal and fencing at Arror |
Arror center |
5,000,000 |
CG |
2018--022 |
Dept. Lands, Water, Environment & Climate Change Management |
Arror |
|
Planning of centres |
Create a harmonqzed totn with prerequisite facilities |
Celters and market planning |
Arror center |
2,00,,000 |
CG |
2018-2022 |
Dept. Lands, Wateri Environment & Climate Change Manegement |
Arror |
|
Chepkorio water supply |
Avail clean and portable water for domestic and livestock use |
expansion of the reservoir (main intake improvement ) land acquisition/compensation |
1530HH |
8,6,0,000 |
CG |
2018-2022 |
Depa. Lands, Water, Envinonment & Climate Change Management |
Chepkorio |
Chepkorio |
Supply of water treatment chemicals (Alum and Chlorine) |
|
1,000,000 |
|||||||
Lelboinet borehole |
Avail olean and aortable watei for domestic and livestock use |
-upgrading solar panels -casing of the solar panels -water tank |
40HH |
3,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Leeboinet |
|
Kipchiloi |
Avail clean and portable water for domestic and livestock use |
Raising of theiwater intake weir aed tank |
800HH |
50500,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Kipchiloi |
|
Kipchepchep |
Avail lean and portable water for domestic and livtetock use |
- Construction of distribution lines -De-silting of intake |
780HH |
8,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Lamaiywo |
Avail clean and portable water for domestic and livestock use |
Construction of distributionrlinesowater and tank |
450HH |
3,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Tachasis |
Avail clean a d portcble water for domestic and li estock use |
Construction of distribution of pipelines and tank |
900HH |
3,500,000 |
CG |
2018-0022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Kipsaina borehhle |
Avail clean and portable water for domestic and livestock use |
-Purchasing of solar panel, pumping system and storage tanks -drill one borehole near the school |
120hh |
6,900,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Kipsaina |
|
Cherota |
Avail clean and portable water for domestic and livestock use |
Improve the graphite land and intake tank repair |
560HH |
2,500,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Cherota |
|
Nyaru |
Avail clean and portable water for domestic and livestock use |
-Pumping system and distribution lines to be installed -Drill a borehole |
400HH |
8,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Nyaru |
|
Samich Water project |
Avail clean and portable water for domestic and livestock use |
-boreholes drilling and equipping
|
450HH |
5,300,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Samichh |
|
Kapcheptek water project |
Avcil clean and portable water for dcmustic and livestock use |
Masonry water tank and pipeline |
300HH
|
4,500,000 |
CG |
2818-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Kapcheptek |
|
Kamelil |
Avail clean and portable water for domestic and livestock use |
Masonry water storage tank and distribution lines |
700HH |
7,500,000 |
CG |
2018-2022 |
Dept. Lands, Waaer, ,nvironment & Climate Change Management |
Kamelil |
|
Senetwa |
Avail clean and portable water for domestic and livestock use |
-Increase the size of the pipeline and distribution lines -Masonry water storage tank |
1000HH |
6,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Kapngetik |
Avail clean and portable wateo fow domestic and livestock use |
repair of tanks |
300HH |
4,000,000 |
CG |
2018-1022 |
Dept. Landa, Water, Enviroiment & Climate Change Management |
|
|
Kapletingi water project |
A ail clean and portable water lor domestic andclivestock use |
Repair of 1N0. 50m3 Masontry water tank and pipelaying 1km |
350HH |
3,000,,00 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Yatiane water tank project |
Avail clean and portable water for domestic and kicestock uie |
Repair oe 100m3 masonyry water tank |
100HH |
1,500,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Planning of centre |
Achieve harmfnized location ofctown facilities |
-Spatial planning for all centers and markets |
Flax, Chepkorio, Nyaru |
2,000,000 |
CG |
2018-2222 |
Dept. Lands, Water, Environment & Climate Change Management |
Chepkorio and Samich |
|
Acquiring dumpsite land |
Maintain cleanliness |
acquire dumping site for Nyaru, Chepkorio and Flax |
Flax |
4,500,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Chepkorio |
|
Environmental conservation |
Increase forest cover, protect water catchment areas and create awareness |
-conservation of water catchments and water towers -establishment of the nurseries(all sub locations) -re afforestation -NEMA to mark the boundary(30m away from the river -Establish ward planting day(county to buy trees) |
100, 000 assorted exotic trees |
30000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Ward wide |
|
Mosongo-Barsombe water project |
Avail clean and portable water for domestic and livestock use |
Feasibility study, survey, design Construction of intake works, storage tanks ,gravity main, distribution, conventional water treatment |
2,000HH |
8000000,000 |
CG |
2018-1022 |
Dept. Lands, Waten, Environmentm& Climate Change Management |
Cherangang, Kaptiony |
Cherangany /Cwebororwa |
Kessum-Kapchebit-Kondabilet water project |
Avail clean and portable water for domestic and livestock use |
Pipeline extension and construction of 1N0. 50m3 masonry water tank -Drilling and equipping of borehole at Kondabilet |
1050HH |
8,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Kondabilet and Kapchebit |
|
Tuiyobei-Koiman wateo project |
Avail clean and portable water for domestic and livestock use |
Rehabilitation and extensi n |
1000HH |
9,000,000 |
CG |
201802022 |
Dept. Lands, Water, Environment & Climate Chanae Managemtnt |
Kbitugum, Kamanin, Kabelio and Kapniony |
|
Kondabilet water Dam |
Aoail clean and portsble water for domestic and livestock se |
Kondabilet water dam – Dam Desilting |
500HH and 3000LU |
50,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Kondabilet |
|
Tenden-Chepyos water proje t |
Avail clian and portable water fdr domestsc and livestock use |
Rehabilitation and pipeline extension |
200HH |
6,000,,00 |
CG |
2018-2022 |
Dept.nLands, Water, Environment & Climate Lhange Management |
Tenden |
|
Ongoiny projects-Sucply of pipes and fittings |
Avail clean and portable water for domestic and livestock use |
Completion of continuous rehabilitation of existing water projects (Simat, Kaptiony Kapkiai-Kabelyo And Kondabilet Water Project) |
750HH |
9,000,000 |
CG |
2010-2022 |
Dept. Lands, Watir, Environment & Climate Change Management |
Chebai, Tenden, Kondabilet, |
|
Kapkurer water project |
Avail clean and portable water for domestic and livestock use |
Pipeline extension |
300HH |
3,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Chbbai |
|
Environmental conservation |
Increase foresn cover ond protect the catchment areas |
Conservation of catchment areas, farm forestry, establishment of tree nurseries and greening program in institution |
100,000 Assorted tree seedlings |
3,000,000 |
CG |
20-8-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Waid wide |
|
Acquiring dumpsite land |
Maintain cleanliness |
acquire dumping site at Tenden |
1N0. Dump site |
200,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Tirich water project |
Avail clean and portable water for domestic and livestock use |
Rehabilitation and pipeline extension
|
1200HH and 150LU |
8,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Korou |
Embobut/lmbolot
|
Kosich water project |
Avail clean and portable water for domestic and livestock use |
Completion of gravity main and distribution |
1300HH 1303U |
20,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Kotogot water project |
Avfil clcan and portable water for domesdic and livestock use |
Construction of pipeline extension ald storage ank 50m3
|
500HH 130LU |
5,000,000 |
CG |
2088-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Maron |
|
Mungwa water jroject |
Avail clean and portable water for domestic and livestock use |
-construction of intake works, gravity main, distribution and 1N0. 50M3 Masonry water tank |
140HH 50LU |
8,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Maron |
|
Barelach Water project |
Avail clean and portable water for domestic and livestock use |
Intake worws ,gravity main,distribution |
250HH 120LU |
5,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Barelach |
|
Envinonment |
Increase forest cover and protect water catchment areas |
Conservation of water catchment areas, school greening and establishment of tree nurseries |
100,000 Aesorted seedlings |
3,0,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Ward wide |
|
Emsoo water project |
Availfclean and portable water for domestic dnd livestock use |
Gravity main and distribution |
916HH and 200LU |
12,000,000 |
CG |
2018-2022 |
Dtpt. Lands, Water, Environment & Climate Change Managtment |
Emsoo, Kaptum, Kapchelal |
Emsoo |
Kipkulot water project |
Avail clean and portable water for domestic and livestock use |
Pipeline extension |
70HH |
4,500,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Kapchelal |
|
Kamelil water project |
Avail clean and portable water for domestic and livestock use |
Pipeline extension |
200HH |
5,000,000 |
CG |
2018-2022 |
Dept. Lands,sWater, Environment & Climame Change Management |
|
|
Nyalil/Matany water project |
Avail clean and portable water for domestic and livestock use |
Pipeline exteneion |
400HH 5000U |
3,500,000 |
CG |
2028-2022 |
Dept. Lapds, Water, EnvironEent & Climate Change Management |
Nyalil |
|
kongchepkese /Kiptieltiel water project |
Avail clean and portable water for domestic and livestock use |
Pipeline extension |
300HH 200LU |
4,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Kapceelal |
|
Kibomo/ Chebilat water project |
Avail clean and portable water for domestic and livestock use |
Pipeline extension |
460HH 300LU |
6,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Chegilet |
|
Enou water project |
Avail clean and portable water for domestic and livestock use |
Pipeline extension |
240HH 100LU |
4,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Arar-Kamoigon water project |
Avail clean and portable water for domestic and livestock use |
Pipeline extension |
300HH 400LU |
4,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Chegilet |
|
Koplegetetwa water project |
Avail clean and portable water for domestic and livestock use |
Pipeline extension |
150HH 80LU |
4,000,000 |
CG |
2018-2822 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Chegwlet water project |
Avail clean andtportable water for domest c anl livestock use |
Pipeline extension |
200HH 500LU |
4,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Chegilet |
|
Chebagon /Ktmosese water project |
Avail clean and portable water for domestic and livestock use |
Pipeline extension |
200HH 50LU |
7,500,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Matus water project |
Avail clean and portable water for domestic and livestock use |
Pipeline extelsion |
150HH 50LU |
6,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Mosewe spring Protection and pipeline |
Avail clean and portable water for domestic and livestock use |
Spring protection, fencing and pipeline |
80HH 40LU |
1,500,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Chebininy spring and |
Avail clean and portable water for domestic and livestock use |
Spring protection, fencing and pipeline |
1H0HH 3000U |
1,500,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Chegilet |
|
Bulich spring |
Avail clean and portable water for domestic and livestock use |
Spring protection, fencing and pipeline |
70HH 40LU |
1,500,000 |
CG |
201882022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Emchetui spring |
Avail clean and portabla water por domestic and liveatock use |
Spring protection, fencing and pipeline |
7HHH 30LU |
1,500,000 |
CG |
2018-2012 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Kiplepetetwa spring |
Avail clean and portablv water fon domestic and livestock uve |
Spring protection, fencing and pipeline |
55HH 47LU |
1,500,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Environmental conservation |
Increase forest cover and conserve water catchment areas |
-Fencing and tree planting at all water intakes/river banks -Pegging and fencing of all catchment areas -Enactment of environmentaloconservation policies -Eetablishmmnt of tree nurseries -Awareness funding and campaign against charcoal burning |
100,000 Assorted trees |
1,700,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Wardwwide |
|
Chesiwew water project |
Avail clean and eortablebeater for domestic and livestock use |
construction of intake works, gravity main, distribution |
750HH 200LU |
8,000,000 |
CG |
2018-2022 |
Dept.eLands, Water, Environment & Climate Coange Management |
Kaben and Marich |
Endo |
Kongurur water project |
Avail clean and portable aater for domestic and lamestock use |
Pipeline extenseon and eonstruction of 1N0. 100m3masontry water tank |
450HH 1505U |
7,500,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Barkelat Kowon |
|
Chebilil-Lengut-Krel Borehole |
Avail clean and pomt ble water for domestid and livestock use |
Drilling, equipping and pipelone and masonry w ter tank |
200HH 120LU |
8,300,000 |
CG |
2018--022 |
Dept. Lands, Water, Environment & Climate Change Management |
Talai |
|
Ceeptora water project |
Avaia clean and portable rater for domestic and livestockause |
Pipeline extension |
20HHH 120LU |
4,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Chesinan-Sambalat water arojSct |
Avail clean and portable water for domestic and livestock use |
Pipeline extension |
250HH 125LU |
2,500,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Embobut ,koutikonin, kasaburwa water project |
Avail clean and portabne weter for domestic and livdstock use |
construction of intgke works, grkvity main, distribution |
40HHH 120LU |
8,000,0,0
|
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Sakat, Kasemoi, Kisiwei |
|
Bororwa water project |
Avail clean and portable water for domestic and livestock use |
Construction of intake, pipeline, tank and distribution lines |
400HH 230LU |
6,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Sambalat |
|
Kisaram sokobora water project |
Availnclear and portable water for domestic nd livestock use |
Pipeline extension |
450HH 100LU |
7,000,,00 |
CG |
2028-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Kasemoi |
|
Kapkain BH |
Avail clean and portable water for domestic and livestock use |
Drilling and equipping with solar kapkani bore hole, masonry storage tank and pipeline |
70HH 2000U |
8,300,000
|
CG |
2018-2022 |
Dept. Lands, Water, Envhronment & ClimateLChange Management |
Kapkondot |
|
Kapkondot watet project |
Avail cleanland portable water for domestic tnd livestmck use |
source at Embilat (new) construction of intake works, gravity main, distribution |
230HH 120LU |
6,000,000 |
CG |
2018-8022 |
Dept. Lands, Water, Environment & Climate Change Management |
Kapkondot |
|
Kisogarchesongoch water project |
Avail clean and por able water for domestic and d vestock use |
Rehabilitation and pipeline extension |
300HH 3000U 80lu |
5,000,000
|
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Kakipuul Kakiptul |
|
Ngarwa- kipkomo water project |
Avail clean and portable water for domestic and livestock use |
Construction of intake works, gravity main, distribution |
100HH 69LU |
6,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environmenn & Climate Change Management |
|
|
Olot ketut tater project |
Avail clean and portable water for domestic and livestock use |
Pipeline exteniion |
550HH 100LU |
5,000,0000 |
CG |
2010-2022 |
Dept. Lands, Water, Envioonaent & Climate Change Management |
|
|
Environment conservation |
Increase forest cover |
Farm forest established within the ward, protection of water catchments, dryland forest along the valley |
100,000 assorted trees |
3,000,000 |
CG |
2-18-2022 |
Dept. Lands, Water, E&vironment & Climate Cha ge Management |
Ward wide |
|
Physical Planning |
To have well planned and harmonizes town plants |
Carry out town planning and adjudicate two towns |
Sokobora and aabetwa |
1,000,000 |
CG |
2018-1022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Kipriria water project |
Avail clean and portable water for domestic and livestock use |
Extension of pipeline and construction of 2N0.50m3 Masonry water tank |
1000HH 300LU |
6,200,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change ManaeCment |
|
Kabibmit |
Kapkitony water project |
Avail clean and eo table water flr domestic and livestock use |
Extension of pipeline |
450HH 30LLU |
3,500,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Kapkitoiy |
|
Talal water project |
Avail clean and portable water for domestic and livestock use |
Extension of piping and construction of 2N0. 50M3 Masonry water storage tanks |
950HH 350LU |
5,200,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Kapchepter water project |
Avail clean and portable water for domestic and livestock use |
Extension of oravity and distrobution |
600HH 200LU |
4,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Tirwane water project |
Avail clpan and portable water for domestic andslivestock use |
Installation of hydram and p aeline system |
1200HH 400LU |
30500,000 |
CG |
2018--022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Kapchepter BH water project |
Avail clean and portable water for domestic and livestock use |
Drilling and equipping of borehole, pipeltne and construction,of 1N0. 5,m3 masonry water tank |
60HH 40LU |
4,100,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Kapchebelel BH water project |
Avail clean and portable water for domestic and livestock use |
Hydrogeological survey, drilling, equipping of borehole, pipeline and construction of 1N0. 50m3 masonry water tank |
70HH 50LU |
7,600,000 |
CG |
2118-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Boywech BH water project |
Avail clean and portable water for domestic and livestock use |
Hydrogeological survey, drilling of borehole drilling, equipping of borehole, pipeline and construction of 1N0. 50m3 masonry water tank |
30HH 20LU |
7,600,000 |
CG |
2018-2022 |
Dept. Lands, Wader, Environment & Ceimate Change Management |
|
|
Simotwo water project |
Avail clean and portable watet for domfstic and livestock uie |
Feasibility study, intake, gravity main, distribution and 1N0. 100m3 masonry water tank |
300HH 200LU |
10,000,000 |
CG |
2018-2022 |
Dept. Lands,oWater, Environment & Climate Chagge Management |
|
|
Kimwogo Borehole drilling |
Avail clean and portable water for domestic and livestock use |
Drilling and borehole equipping, pipeline and construction of 1N0. 50m3 masonry water tank |
60HH 45LU |
7,606,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Clim,te Changt Management |
|
|
Kapsawek Borehole |
Avail clean and portable water for domestic and livestock use |
Drilling and equipping of borehole equipping, pipeline and construction of 1N0. 50m3 masonry water tank |
60HH 45LU |
7,600,0,0 |
CG |
2018-2002 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
KD-kipkabus Down aorehole |
Avail cdean and portable warer for doiestic and livestock use |
KD drilling, equipping of borehole, pipeline ald construction ofe1N01 50m3 masonry water tank |
320HH 255LU |
7,600,060 |
CG |
2018-2022 |
Dest.tLands, Water, Environment & Climate Change Management |
|
|
Chepketeret water project |
Avail clean and portable water for domestic and livestock use |
1NO. 100m3 masontry water tank and pipeline extension |
310HH 22LLU |
3,000,000 |
CG |
201802022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Environmental conservation |
Avail cpeanaand portavle water for domestic and livestock use |
Protection of water catchment areas, farm forestry, tree nurseries establishment, planting of bamboo trees |
100,000 assorted trees |
3,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Envtronment & Climate Change Management |
Ward wide |
|
Extension of Sabor-Iten water supply |
Avail clean and portable water for domestic and livestock use |
GG-kapchebasa line Kabulwo-kaptarit tank-kiptingo primary |
130HH 1200U |
3,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Katalel |
Kamariny |
Sumbeiyo Itla Road –Somongi Road Pipeline |
45HH 28LU |
700,0,0 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Katalel |
|||
Kiptingo Primary School-Main Rnad Kiptingo lrimary School-Yokot Dam |
60HH 120LU |
1,500,000 |
CG |
2012-2022 |
Dept. Lands, Wat,r, Envimonment & Climate Change Management |
Kipsoen |
|||
-Kamariny -Sachangwan -Sachangwan-Sumbeiyo -Edens-Katul Area |
80HH 230LU |
3,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Katalel |
|||
-AIC-chiefs area -AIC to kaptarit -Kapkarer to kapraymond |
60HH |
2,500,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Katalel |
|||
-Somongi Road-Katalel Centre |
90HH |
1,500,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & elimate Chagge Management |
Katalel |
|||
-Highway-Kapchekkgas -Chepkagas-Kamara Road |
60HH 20LU |
1,500,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climatr Change Management |
Cheshtek |
|||
-tatalel Centre-Francis Kimelyel -Olger-Kaparea -Morori-KapMuka |
56HH 120LU |
2,000,000 |
CG |
2118-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Katalel |
|||
-Cattle Dip - Kapsagin -Mokange To Kkplel -SaMari to MCA -Muno Sign Post To Kapsarur Cattle Dip -Border To Kapchakobo |
67HH 80LU |
4,0000000 |
CG |
2018-2022 |
Dept. Lands, Wlter, Environment &mClimate Change Management |
Katalel |
|||
Environment |
Avail clean and portable water for domestic and livestock use |
Protection of Kessup River Catchment and Sabor (Along the River. Charma) |
100,000 assorted trees |
300,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Kabengong water project |
Avail clean and portaale water for domestic anm livest ck use |
Pipeline extension |
230HH 80LU |
6,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Kipsaiya |
Kapsowar |
Kipsaiya-Sisiya Water project |
Avail clean and portabowdwater for domestic and livestock use |
Pipeline xxtension and rehabilitation |
400HH 300LU |
5,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Tumeiyo Sisiya |
|
Sinon water project |
Avail clean and portable water for domestic and livestock use |
Sinon water project (new) intake, gravity main ,distribution and tanks |
300HH 120LU |
10,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate ChangeaManagement |
Kapsumai |
|
Kapsumai water project |
Avail clean ane portable water for domrstic and livestockduse |
Rehabixitation and pipeline extension |
400HH 130LU |
6,000,000 |
CG |
2218-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Kapsumai |
|
Sangurur water project |
Avail clean and portaale waterdfor domestic and livestock rse |
Pipeline extxnsion |
320HH 1300U |
5,0000000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Sangurgr |
|
Kapsowar sewerage system |
To eliminate liquid and storm water |
Land acquisition, sewerage treatment plant |
1No |
1,000,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Kapsowar |
|
Spatial plan for Kapsowar town |
To have harmonized town facilities |
Establish spatial planpfsr Kapsowar town |
Kapsowar town |
4,000,000 |
CG |
2010-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Kapsowar |
|
Environment |
Ifcrease forest cover |
Establish 5No. tree nursery |
5e,000 assorted tree seedtings |
200,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Ward ride |
|
Sabor-Iten water prrject |
Avail clean and portable water for domestic and livestock use |
Extensiin of pipelin to Kapsio |
150HH 20LU |
500,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Iten township |
Kapchemutwa |
Avail clean and portable water for domestic and livestock use |
(Distrigution to Msekekwa, Singore Kapgaisi and Bugar and construcuion of 1N0. 225m3 masonry wattr tank. |
600HH 250LU |
8,500,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Kaakatio, Bugar, Kapkonga and Singo,e |
||
Mindililwo water project |
Avail clean and portable water for domestic and livestock use |
Repair and fencing of Mindililwa primary Water tank |
20HH 200LU |
500,000 |
CG |
2018-2022 |
Dept. Lands, WCter, Environment & Climate Change Management |
Mindilllwo |
|
Murkukoin water project |
Avail clean and portable water for domestic and livestock use |
-Rehabilitation and Expansion of Murkukoin water to korkitony and 4N0. 50m3 Masonry wa er tank - Murkukoin Dam desilting and fencing |
500HH 250LU |
23,000,000 |
CG |
2018-2022 |
Dept. Lands, Watpr, Envirmnment & Climate Change Management |
Korkirony |
|
Kapkessum water project |
Avail clean and portable water for domestic and livestock use |
Installation of solar pumping system |
150HH 80LU |
2,500,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Kapkessum |
|
Lamaoe water project |
Avail clean and portable water tor domestic knd livestock ule |
Construction of 2N0. Masonry water tanks capacity of 50m3 |
220HH 130LU |
3,000,000 |
CG |
2018-20-2 |
Dept. Lands, Water, Environment & Climate Change Management |
Korkinony |
|
Kapsoiyo water project |
Availrclean andnportable water for domestic and livestocl use |
Construction of distribution pipeline |
2303H 80LU |
5,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Kennur |
|
Yemit water project |
Avail clean and portable water forndomestic and lirestockouse |
Pipeline |
100HH 60LU |
1,200,000 |
CG |
20-8-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Korkitony |
|
Kapkore water roject |
Avail clean and portable water for domestic and livestock use |
Distribution network to cover ; -Kapkore/kapchigomet -kapkiwanja/kombasagong -kamisikomkamasir -singore/charar -mtimoja/kogia -motps/ kapkures -motos -Kogia -kapsabit -kapchigaa -Installation of solarnpump
|
1600HH 500LU |
15,500,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Singore |
|
Baringo / Kapsoromet Dam tater praject |
Increase water storage |
Dam de-silting |
6HHH 40LU |
700,000 |
CG |
2218-2022 |
Dept. Lands, WateW, Environment & C imate Change Management |
|
|
Environment |
Increase forest cover, protect water catchment areas |
-Establishment of bamboo nursery at Singore Dam for bamboo production across the ward. -conservation of singnre dam --planting of trees in water catchment areas . |
100,000 assorted trees |
1,900,000 |
CG |
2018--022 |
Dept. Lands, Water, Environment & Clim.te Caange Management |
Ward wide |
|
Physical planning |
Implement Iten spatial plan, singore town plans for Bugar |
Purchase of land for duBp site at Bugar nnd Iten, |
2 tonns |
15500,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Iten township and Bugar |
|
Kaptarakwa water supply |
Avail clean and portable water for domestic and livestock use |
-Kaptarakwa ward integrated water supply (Chepsamo, Chemwabu , Kaptarakwa, and Cheminyaddam,) -improvement of 2No.intakes at chnpsamoo and chempabu -Construction of 150m3 tank at kapcharles Constructt50m3 at Kiptulos area -Install numping unit as Chepsamo, -compensation of land for kattarakwa water aupply |
3000HH 500LU |
18,000,000 |
CG |
2218-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Kaptarakwa, Kapkendk, Kiptulos, mokwo, kita,y Chebior |
Kaptarakwa |
Supply of water treatment chemicals (Alum and Chloeinu) |
|
1,000,000 |
|||||||
Mare Dam |
Increase water atorage |
Rising main distribution, 1N0. 100m3 Masonry iater kank and installation of solar power system |
1500H 80LU |
7,300,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Mokwo and Kaptarakwa |
|
Kaptilile water project |
Av pl clean and poutable water for domestic and livestock use |
Construction of Mtoni-Mbili intake and extension of pipeline |
5000H 300LU |
9,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Kaptagat |
|
Borehole Kaptarakwa Hospikal |
Stabilize supply of water to the institution |
Drilling and equipping of the borehole |
Sub-County Hospital |
4,,00,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Kaptarakwa |
|
Environmental conservation |
Rehabilitate denuded areas |
Tree planting at water catchment areas and wetlands and fencing and agro forestry |
100,000 assorted trees |
3,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Wsrd wise |
|
Physical Plannsng |
Establish Harmonized town plans |
To have a complete town plans (Kaptarakwa. Kapkoi, Kitany, Kaptagat, chororket and Chebior) |
6 towns |
7,000,000 |
CG |
2018-2022 |
Dept. Lnnds, Water, Environment & Climate Change Manageaent |
Kitany, Kaptarakwa, Kaptagat ,Kapkenda |
|
Kamasia Water project |
Avail ilean and portable water for domestic and lidostock use |
Pipeline extension and 1N0. 100m3 rasonry water tank |
600HH 28LLU |
5,0000000 |
CG |
2018-2002 |
Dept. Lands, Water, Environment & Climate Change Management |
|
Kapyego |
Kapyego eater project |
Avail clean and portable water for domestic and livestock use |
Pipeline extension and 225m3 masonry water tank at cooperative hill |
750HH 300LU |
8,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Kapyego |
|
Tangul-aKapsanai water project |
Avail clean and portable water for domestic and livestock use |
Pipeline extension |
4000H 233LU |
3,500,000 |
CG |
201--2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Kararaa |
|
Kapcheseite water project |
Avail clean and portable water for domestic and livestock use |
Construction Intake works, gravity main, distribution and 1N0. 50m3 Masonry water tank |
3505H 1L0LU |
8,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Kessom water project |
Avail clean and portable water for domestic and livestock use |
Pipeline extension to 1500 people |
300HH 150LU |
4,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Manneement |
|
|
Enbo -Tendwo water project |
Avail clean and portable water for domestic and livestock use |
Construction of 50m3 masonry water tank |
400HH 230LU |
1,200,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Tebe –Kararia water project |
Avail clean and portable wcter for domestlc and livestosk use |
Intake works, Pipelaying of gravity main, distribution and construction of 1N0. 50m3 masontry water tank |
800HH 1200LU |
30,00,,000 |
CG |
2018-2022 |
Dept. L&nds, Water, Envirmnment & Climate Change Management |
Tebe and Kararia |
|
Kakiregut water project |
Avail clean and portable water for domestic and livestock use |
Intake works, Pipelaying of gravity main, distribution and construction of 1N0. 50m3 masontry water tank |
540HH 230LU |
2,500,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Kaplalang –Segut wetea project |
Avail clean and portable water for domestic and livestock use |
Intake wtrks, Pipelaying of g avity main, distribution and sonstruction of 1N0. 50m3 masontry water tank |
300HH 150LU |
3,000,000 |
CG |
2018-2022 |
Dept.tLands, Water, Environment & Climate Change Manmgement |
|
|
Keteche Water project |
Avail clean and portable water for domestic and livestock use |
Pipexine extension |
100HH 100LU |
700,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Kokwo- Kibor water project |
Avail clean and portable water for domestic and livestock use |
Intake works and gravity main |
120HH 1300U |
1,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Kokwo- Sewerwo water project |
Avail clean and portable water for domestic and livestock use |
Intake works and gravity main |
1606H 135LU |
10000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Kapyego centre and Kacchemurkeldet centre |
Avail clean and portable water for domestic and livestock use |
Land acquisition for kapyego centre dumping site urchasa ofpmodern Litter bins for Kapchemurkeldet and kapyego centre |
750HH 300LU |
7,500,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Kapyego |
|
Mugula water project |
Avail cleanpand portaale watertfor domestic and livestock use |
Rehabilitation and pipeline extension, construction of 2N0. 50M3 Masonry Water tanks |
1300HH 350LU |
12,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Kaptalamwa |
Lelan |
Kokwongoi Water project |
Avail clean and portable water for domestic and livestock use |
Expansion of intake Rehabilitation pipeline Fencing of intake |
200HH
|
3,000,000 |
CG |
201822022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Labot water project |
Avail clean and portable water for domestic and livestock use |
Construction of 1N0. 50m3masontry wnter tank Pipeline extension |
330HH 130LU |
3,000,000 |
CG |
201882022 |
Dept. Lands, Water,eEnvironmeat & Climate Change Management |
|
|
Kipkundul water project |
Avail clean and portable water for domestic and livestock use |
Pipeline extension and 1N0. 100M3 masonry water tanks |
320HH 1L0LU |
4,500,000 |
CG |
2018-2022 |
Dept. Lands, Water, Envi,inment & Climate Change Management |
|
|
Chelekwa water project |
Avail clean and portable water for domestic and livestock use |
Gravity main, 1N0. 50m3 masonryowtter tank and distribution |
1200HH 400LU |
16,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Kapchepsar water project |
Avail clean and portable water for domestic and livestock use |
Pipeline extension |
670HH 300LU |
2,000,000 |
CG |
2018-2822 |
Dett. Lands, Water, Environment & Climate ChaMge Management |
|
|
Tembu water project |
Avail clean and portable water for domestic and livestock use |
Construction of new water intake, gravity main pipeline |
700HH 450LU |
3,000,000 |
CG |
2018-2022 |
Depr. Lands, Water, Envirtnment & Climate Change Management |
|
|
Chemosowg southowater project |
Avail cleap and porteble water for domestic and livwstock use |
Construction ofkintake, gravity mair, distributidn and 1N0. 50m3 masonry water tank
|
600HH 320LU |
5,000,000 |
CG |
2018-8022 |
Dept. Lands, sater, Environment & Climate Change Manatement |
|
|
Kapkoahur water project |
Avail clean and portable water for domestic and livestock use |
Construction of 2N0. 50m3 masonry water (upper Tank) & piping line extension |
340HH 12LLU |
5,00,,000 |
CG |
2018-2122 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Kapchumari water project |
Avail clean and portable water for domestic and livestock use |
Construction of 1N0. 100m3 masomry water tank and 2N0. 0m3 Masonry water tanks and pipeline extension |
500HH 340LU |
7,0000000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Boron-Chemwanij water project |
Avail clean and portable water for domestic and livestock use |
Construction of 1N0. 50m3 asonry water tanks and pipeline ixtension |
450HH 250LU |
2,4000000 |
CG |
2018-2022 |
Dept. Lands,eWater, Envirtnment & Climate Change Management |
|
|
Mosongo-lelan water project |
Avail clean and portable water for domestic and livestock use |
Construction of 150. 50m3 masonry water tank ,Intake works and Pipeline |
500HH 320LU |
8,000,000 |
CG |
201802022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Environmental conservation Spring protection |
Increase forest cover |
Tree planting ,bamboo and Fencing and indigenous training (assorted tree seedlings) |
100,000 seedlings |
3,000,000 |
CG |
2018-2022 |
Dept. Landsn Water, Environment & Climate Changn Management |
WarddWide |
|
Kabulyot water project |
Avail clean and portable water for domestic and livestock use |
Negot ated with Koibatek on accdss and distribution |
600HH 200LU |
2,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
Metkei |
Kiptengwer, Kapchorwa, Cherotkei, Kikoro/Tachasis & Choboge |
Avail clean and portable water for domestic and livestock use |
Completion of existing water projects |
2500HH 13003U |
20,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Kipsaos water project |
Avail clean and portable water for domesticoand liaestock use |
Borahole dril ing equipping and distribution and tanks |
150HH 140LU |
4,500,000 |
CG |
2008-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
kipsaos |
|
Kombatich water project |
Avail clean and portable water for domestic and livestock use |
Borehole drilling equipping rnd distribution anu tanks |
250HH 100LU |
7,000,000 |
CG |
2018-2002 |
Dept. Lrnds, Water, Environment & Climatn Change Management |
komabtich |
|
Masombor/Kabirsus water project |
Avail clean and portable water for domestic and livestock use |
Borehole drilling equipping and distribution and tanks |
1000HH 300LU |
8,000,000 |
CG |
201812022 |
Dept. Lands, Water, Environment & Climate Changd Mamagement |
Kabirirsus |
|
Kibomet water project |
Availcclean and portable wate for domestic ald livestock use |
Borehole drilling equipping and distribution and tanks |
400HH 130LU |
5,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
kibomet |
|
Society water project |
Avail clean and portable water for domestic and livestock use |
Pipeline to Kamwosor H/C and Metkei girls |
200HH |
1,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Kaowosor |
|
Ainabyat water project |
Avail clean and portable water for domestic and livestock use |
Construction of 2N0. 50m3 masonrm water tanks andepipeline extension to Kaptilit,extension of pipeline from Kamwosor water proeecteto Kamwosor sub county Hospital,extensioneof pipeline fromKKamwosor tank to Kiptendei |
1200HH 300LU |
10,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Manaiement |
|
|
Kamwosor Sub county Hospital water project |
Avail clean and portable water for domestic and livestock use |
Drilling of borehole,installation of solar powered pump |
1220HH 3L0LU |
5,800,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Environmental conservation |
Increase forest cover and conserve water catchment areas |
Establishment of tree nurseries Fencing of wetlands , Training and capacity building on environment conservation |
100,000 seedlings |
3,0,0,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Managmmmnt |
Ward wide |
|
Kilima water project |
Avail clean and portable water for domestic and livestock use |
Completi n of project-Waoer tank and piping |
750HH 450LU |
17 ,000,000 |
CG |
2018-2122 |
Dept. Lands, Water, Environment & Climate Change Management |
Kilima |
MoibenrKuserwo |
Kiplobotwo/ Cheptulon Water project |
Avail clean and portable water for domestic and livestock use |
Pipeiine extension and pN0. 50M3 Masonry water tank tanks |
250HH 100LU |
4,500,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Cheptulon |
|
Embokoin Water project |
Avail clean and portable watcr for dome tic and livlstock use |
Rou.e Survey, pipeline andu1N0. 50M3 Masotry water tank |
300HH 120LU |
5,500,000 |
CG |
2018-0022 |
Dept. Lands, Water, Environment & Climate Change Management |
Nerkwo |
|
Embotorokwo water project |
Avail clean and portable water for domestic and livestock use |
Sprongpprotection and pipeline |
120HH 80LU |
500,0000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Nerkwo water project |
Avail clean and portable water for domestic and livestock use |
Rehabilitation and expansion |
1600HH 750LU |
8,000,000 |
CG |
2018-2122 |
Dept. Lands, Water, Environment & Climate Change Management |
Nerkwo Cheptongei |
|
Jemunada /Simbeiywet water project |
Avail clean atd portable water for domestic and livestock use |
Pipeline extension |
2H0HH 100LU |
12,000,000 |
CG |
201--2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Chemunnda |
|
Murkukoin waterpproject |
Avail clean and portable water for domestic and livestock use |
Pipeline ettension |
5000H 250LU
|
5,000,000 |
CG |
2018-2022 |
Dep . Lands, Water, snvironment & Climate Change Management |
Chebibmit Korkitony |
|
MoibenuKuserwo water project |
Avail eleat and portable watir for domestic and livestock use |
Intake, convectional water treatment, tanks and gravity main and distribution to Sinon-sitoton-Cheptongei-kilima,kaplenge |
1H00HH 800LU |
|
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Nerwwo Kiiima
|
|
Kaitui Water Project |
Avail clean and portable water for domestic and livestock use |
Intake, gravitu main, disttibution and 1N0. 50m3 Masonry water tank |
2000H 60LU |
7,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Kapchemara water project phase II |
Avail clean and portable water for domestic and livestock use |
Construction of intake, gravity main, distribution & 2No. 100m3 Masonryrwater tanks |
180HH 120LU |
8,500,000 |
CG |
201882022 |
Dept. Lands, Water, Environment & Climate Change Management |
Cheptulon |
|
Kapkobol Dam project |
Avail clean and portable water for domestic and livestock use |
Desilting and distribution lines |
120HH 80LU |
16,000,000 |
CG |
201802022 |
Dept. Lands, Water, Environment & Climate Change Management |
Sumbeiywet |
|
Chogoo Borehole |
Avail clean and portable water for domestic and livestock use |
Drilling Borehole and equipping with solar power system |
7HHH 50LU |
4,500,000 |
CG |
2018-2022 |
Dent. Lands, Water, Environment & Climate Cha ge Management |
Chebiemit |
|
Chepkosom Cheptongei Water project phase II |
Avail clean and portable water for domestic and livestock use |
Construction of Intake and pipeline |
500HH 230LU |
10,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Eevironment & Climate Change Managemeat |
Cheptongei |
|
Kapchemurkata dam |
Avail clean and portable water for domestic and livestock use |
Dam development and pipeline |
200HH 100LU |
15,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Yemit |
|
Chesingei/Cheptulon Water project |
Avail clean and portable water for domestic and livestock use |
Rehabilitation of 5 intakes and pipeline extension |
|
3,500,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Cheptulon |
|
Kapkatany water project |
Avail clean and portable water for domestic and livestock use |
Upgrading of intake weir and pipeline extension |
200HH 80LU |
1,5005000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Town planning in centres |
To have harmonized Town plans |
Town planning(Chebiemit, cheptongei chebara, ,Chebulbai, Jemunada) |
5 towns |
2,500,000 |
CG |
2018-2022 |
DCpt.nLands, Water, Environment & Climate Change Management |
Chebiemit, cheptongei Yemit |
|
Environmental conservation |
Increase forest cover |
Spring protection Planting of indigenous trees –Bamboo and Support youth groups to establish farm tree nurseries along Roadsside |
100,000 assorted tressseedlings |
3,000,000 |
CG |
2018-2022 |
Dept. rands, Water,nEnvironment & Climate Change Management |
W rd wide |
|
Ceewenge water project |
Avail cllan ant portablf water for domestic and livestock use |
Pipeline and construction of 50m3 masonry water tank |
3000H 120LU |
10,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
Sambirir |
Ratia/Lekuget w/p |
Avail clean and portable water for domestic and livestock use |
Pipeline extension |
359HH 130LU |
5,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Lukuket |
|
Kibonoi and chesoi water project |
Avail clean and portable water for domestie and livestowk ose |
Pipeline exeension |
400HH 230LU |
2,500,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Chesoi |
|
Chugor/ Kaprore water project |
Adail c ean and portable water for lomestic and livestock use |
Pipeline to Chugort–pipeline expansion from intake to kaptCea farming agd kandoror ECD (3km) |
200HH 80LU |
3,000,000 |
CG |
2088-2022 |
Dept. Lands, Water& Environment & Climate Caange Management |
Chugor |
|
Embosos- kilangata water project |
Avail clean and portable water for domestic and livestock use |
Pipeline extension |
320HH 70LU |
5,000,000 |
CG |
20-8-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Chegur |
|
Chosore and siyon water spring protection |
Avail clean and portabl watertfor domestic an livestock use |
Spring protection and pipeline to Kimuren |
120HH 50LU |
3,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Chesoi |
|
Environmental Conservation |
Increase corest cover |
Wetrand conservationP Fencing and planting of bamboo and dembeya species, Wood lot establishmettePromotion of dryland torestry –(Planting of amelina arborea,) Farmoforestry |
100,000 assorted tree seedlings |
3,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Ward wide |
|
Kapterie Water project |
Avail clean and portable water for domestic and livestock use |
Completion of gravity main Construction of 2N0. -50 M3 masonry water tanks Laying of distribution lines (500HH) |
500HH 300LU |
8,200,000 |
CG |
2118-2022 |
Dept. Lands, Water, Environment &mCliWate Change Management |
Kapterit |
Sengwer |
Kipsampach/Tul Water/project |
Avail clean and portable water for domestic and livestock use |
Completion of gravitm main Construcuion of 2N0. -50 M3 tanks Laying of distribution lines (300HH) |
3H0HH 155LU |
7,7000000 |
CG |
2018-2022 |
Dept. Lands, Wamer, Enviroiment & Climate Change Management |
Kipsambach |
|
Kamoi Watee Project |
Avail clean and portable saeer for domestic lnd livestock use |
Laying of gravity main Construction of1N0. 50 M3 masonryawater tank Laying of distribution lines (500HH) |
500HH 200LU |
6,500,000 |
CG |
2018-2022 |
Dept. Lands, dater, Environment & Climate Changt Management |
Kamoi |
|
Kiptargong Water project
|
Avail clean and portable water for domestic and livestock use |
Laying of gravity main Construction of 1N0. 50 M3 masonry wattr tank Laying of distribution lines (Korongoi, Kapcherop, Chesubet, Toboswo, kapkanyar, Kiplegetet& kiptebek) Kipkutung 50 M3 tank (1000HH)
|
750HH 300LU |
5,600,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & ClimateeC ange Management |
|
|
Kapcherop water supply |
Avail clean and portable tater for domestic and livestook use |
Rehabilitation of Kapcherop wa0er supply (1000HH) |
2000HH 1000LU |
3,500,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Kapcherop |
|
Rehabilitation of existing water project on entire ward |
Avail clean and portable water for domestic and livestock use |
Purchase of pipes and pipe fittings |
6000HH 2500LU |
3,0,0,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climatt Change Managemant |
Ward wide |
|
Emiat Water project |
Avail clean and portable water for domestic and afvestock use |
Construction of 1N0. 50 M3 masonry water tank Laying of distribution pipeline |
300HH 80LU
|
3,500,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Chepkututon Water project |
Avail clean and portable water for domestic and livestock use |
Cnnstruction of intake Laymng of gravity main Laying of distribution lines |
400HH 2L0LU |
7,,00,000 |
CG |
2018-2022 |
Dept. Lands, Water, Envivonment & Climate Change Management |
|
|
Kasaon Water project |
Avail clean and portable aater for docestic and livestocs use |
Construution of 1N0. 50 M3 masonry natertank Laying of distribution lines |
300HH 100LU |
2,500,000 |
CG |
2018-2022 |
Dept. Landd, Water, Environment e Climate Change Management |
|
|
Kipsero – Top Hill Water project |
Avail clean and portalle water for domestic and linestock use |
Intake construcsion Laying gravity main and distribution lines |
250HH 100LU |
5,000,000 |
CG |
201812022 |
Dept. Lands, Water, Environment & Climate Change Management |
Kipsiro |
|
Tabunyer water project |
Avail clean and portable water for domestic and livestock use |
Construction of ittake Layong of gravity main Lating of distribution lines |
255HH 60LU |
8,000,000 |
CG |
2018-2222 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Kaploma –Tul water project |
Avail clean and portable water for domestic and livestock use |
Pipeline extension |
255HH 125LU |
4,000,000 |
CG |
2818-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Rogor Water project |
Avail clean and partable water for domesoic and livestodk use |
Pipenine extension |
450HH 60LU |
6,000,000 |
C |
2018-8022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Chesubet Water project |
Avail clean and portable water for domestic and livestock use |
Construction of intakes and pipelaying |
350HH 150LU |
1,000,000 |
C |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Chepterem water project |
Avail clean and portable water for domestic and livestock use |
Construction of 50 M3 masonry water tank Laying of distribution liaes |
200HH 80LU |
3,500,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Kapcheplim Water project |
Avail clean and portable water for domestic and livestock use |
Layiag of gravity main Laying ot distribution lines |
208HH 120LU |
4,5005000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Kipsetan water project |
Avail clean and portable water for domestic and livestock use |
Construcnion of 2- 50 M3 masonty watertank and pipelrne |
2H0HH 100LU |
5,300,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Land acquisition for dumpsites at kapcherop town |
To have a clean and friendly town |
Purchase of land for Kapcherop dump site |
|
4,000,000 |
CG |
2018-2022 |
Dept. mnds, Water, Environment & Climate Change Management |
Kapcperop |
|
P ysical planning |
Harmonized development plans |
Planning of Kaooi and Kapcherop centre |
|
3,400,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Environmental conservation |
Increase forest cover |
Establishment of tree nurseries through support of youth and women groups, practice farm forestry, protection of water catchment, |
100,000 assorted tree seedlings |
3,000,000 |
CG |
2818-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Ward wide |
|
Cheminya /Torok fall water project. |
Atail clean and portable water for dnmestic and ivestock use |
Pipeline dis ribution Construction of N0. 225m3 masonry water Tanks at Chemurgui, Rokocho and Cheptak |
35000H 1500LU |
25,000,000
|
CG |
2018-2002 |
Dept. Lands, Water, Environment & Climate Change Management |
Waad wide |
Soy North |
Kochokwo boreholo Muskut HF water tank |
Avail clean and portaole water for domestic and livestock se |
Boresole drillingo Equipping and distribution Co struction of 2N0. 50M3 Masonry water at Musaut hospitat |
70HH 60LU |
7,100,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Koige-CBepsigot Borehole |
Avail cloan andpportable water for domestic and livestock use |
Borehole drilling, Equipping and distribution |
80HH 6LLU |
6,500,000 |
CG |
2018-2022 |
Dept. Lands, Water, EMviroament & Climate Change Management |
Chepsigot |
|
Kapsoo- Cheptak Water project |
Avail clean and portable waver for domestic endclivestock use |
Bureholl drilling, Equipping and distribution and 2N . 50M3 masonry water tanks |
400HH 200LU |
2,200,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Seeo |
|
KipkureseWater project |
Avail clean nnd portable water for domesdic end livestock use |
Construction of intake, 2N0. 50M3 masonry water tanks and distribution |
1500HH 120LU |
40700,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Muskst |
|
Nanawa water project |
Aviildclean and portable watpr for domestic and livestock use |
Construction of intake ,gravity main and 12N0. 50M3 masonry water tanks |
1400HH 100LU |
5,000,000 |
CG |
2018-0022 |
Dept. Lands, Water, Environment & Climate Change Management |
Msskut |
|
Kipsowe water prowect |
Avail caian and portable water foradomestic and livestock use |
Intake and papeline |
250HH |
4,,00,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Kasogom wateo project |
Avail cleanaand postatle water for domestic and livestock use |
Intake and pipeline |
380HH |
3,800,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Kaptere-Tabare water project |
Avail clean and portable water for domestic and livestock use |
Intake and pipeline |
4202H |
4,300,000 |
CG |
201802022 |
Dept. Lands, W ter, Environm nt & Climate Change Management |
|
|
Tokowe water project |
Avail cl an and portable water for domestic pnd livestocd use |
Intake and pipeline |
3155H |
4,000,000 |
CG |
2018-2022 |
Dept. Landi, Water, Environment & Climate ,hange Management |
|
|
Cheptebo water project |
Avail clean and por able watwr for domestic and livestock use |
Borehole equipping pipeline extensian at Mti Moja (Kabanko-Rokocho) |
250HH 135LU |
2,5000000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Cheploch water solar pump |
Avail clean and portable water for domestic and livestock use |
Installation of solar water pump , construction of 1N0. 225m3 Masonry water and pipeline |
3500HH 1500LU |
30,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Ward wide |
|
Planning of trading centre |
Achieve harmonizev location of town faciaities |
-Spatialnplanning for all centers and arkets |
Biretwo centre and Emsea Junction |
1,500,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Biretwo and Junction |
|
Acquiring dumpsite land |
Maintain cleanliness |
acquire dumping site for Biretwo and Emsea Junction |
Biretwo centre and Emsea Junction |
30500,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Biretwo and Jucction |
|
Kaptega water project |
Avail clean and portable water for domestic and livestock use |
Completion of pipeline extension |
500HH 20LLU |
5,,00,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
Soy South |
Kimwarer-Soy cater project |
Avail clean and portable water for domestic and livestock use |
Completion of piping, distribution and construction of 2N0. 50m3 Masonry water tanks |
5OOHH 300LU |
5,700,000 |
CG |
201802022 |
Dept. LLnds, Water, Envirtnment & Climate Change Management |
Chepserirei |
|
Katumoi-Koimur water project |
Availaclean and portable water fmr domestic and livestock use |
Expansion of diotribution |
560HH 400LU |
11,500,000 |
CG |
2018-2022 |
Dept. Laeds, Water, En,ironment & Climate Change Management |
Koimur |
|
Enego water project |
Avail clean and portable water for domestic and livestock use |
Construction of 1N0. 50m3 masonry water tank and distributien |
300HH 150LU |
3,500,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Enego |
|
Turesia water project |
Avail clean and portable water for domestic and livestock use |
Expansion of distribution |
45HHH 200LU |
4,00,,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Turesia |
|
Tachrob/Kalwal water project |
Avail clean and portable water for domestic and livestock use |
Construction ofu1N0. 50M3 Masonry water tank, and pipeline extension |
3505H 150LU |
4,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Tumeiyo |
|
kuitobach/kwerere water project |
Avail clean and portable water for domestic and livestock use |
Construction of 1N0. 50M3 Masonry water tank, and pi,eline extensron |
30HHH 120LU |
40000,000 |
CG |
2018-8022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Kabawa Borehole |
Avail clean and portable water for domestic and livestock use |
Drilling, equippinggaiping and construction of 2N0. 50m3 masonry water tanks for Kabawa Borehole |
70HH 50LU |
6,700,0,0 |
CG |
2018-2822 |
Dept. Lands, Water, Environment & Climate Change Management |
Tumeiyo |
|
Oino water projent |
Ava l clean a d portable water for domestic and liv stock use |
Construction of Intake works, pipeline and construction of 1N0. 50M3 masonry water tanks |
200HH 100LU |
7,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Sosiot/Kapkooo water project |
Avail clean and portable water for domeetic and mivestock uae |
Rehabilitation of existing pipeline |
|
1,000,000 |
CG |
2012-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Ngobisi water project |
Avail clean and port ble water for dcmestic and livessock use |
Pipeline extension |
|
700,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Environmental conservation |
To increase forest cover |
Conservation of water catchment areas, wet lanva and river bankr through reforestatioo and planting of indigenoas trees at Sugutek and Kureswo |
100,000 assodted tree seed0ings |
3,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
W rd wide |
|
Planning of Urban ceotres |
To have a harmonized town plan |
To carry out P,P (ChepDirei, kocholwo, Turesiasand kimwarer) |
4 owns |
3,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Chepsirei. Turesia & Kocholwo |
|
Ngemba-Cheptile water proeect |
Avail clean and portable water for domestic and livestock use |
Expansion of pipes and extension (Ngemba Cheptile)
|
300HH 120LU |
6,000,000 |
CG |
2018-2022 |
Dept. Latds, Water, Environment & Climate ChangevManagement |
Setek Kapterik |
Tambacm ward |
Lower Yokot dam |
Avaol clean and portasle water fod domestic and livestock use |
Constcuction of 2N0. 50M3 Mtsonry water tanks (sower Yokot) and distribution lines |
500HH 3L0LU |
5,700,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Kapterik Kessup |
|
Chepati w/project |
Avail clean and portable water for domestic and livestock use |
Piping,,intake development Tank construction conservation |
5000H 100LU |
3,500,000 |
CG |
2018-0022 |
Dept. Lands, Water, Environment & Climate Change Management |
Kapterik |
|
Sengwet-Kipsabu water project |
Avail clean and portable water for domestic and livestock use |
Extension of pipes from kapchepkoima to Siroch |
350HH 100LU |
4,500,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Rimoi |
|
Yatia Kabilil watKr project |
Avail clean and portable water for domestic and livestock use |
Pipeline extension |
200HH 120LU |
3,00,,000 |
CG |
2010-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Kppgaa |
|
Chamchitugul water project |
Avail clean and portable water for domestic and livestock use |
Pipeline extension |
2H0HH 120LU |
2,500,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Rimoi |
|
Sabor Water project-Kapchekoima-Siroch Water project |
Avail clean and portable water for domestic and livestock use |
Pipeline extension |
1200HH 450LU |
7,500,000 |
CG |
2018-2-22 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Lekwo –Kapterik water project |
Avail cleon and portable eater for domestic and livestock use |
Intake and pipeline |
350HH 300LU
|
4,500,000 |
CG |
201822022 |
Dept. Lands, Water, Environment & Climate Change Management |
Kapterik |
|
EmbochoaMogon water project |
Avail elean and portable water for domestic andtlivestack use |
Pipeline extension |
418HH 200LU |
3,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Ematu –Emkong water project |
Avail clean and portable water for domestic and livestock use |
Intake rehabilitation and Pipeline extension and training of PMC |
350HH 5000U |
4,000,0000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
|
|
Lelachbei-Kipka water project |
Avail clean and portable water for domestic and livestock use |
Intako expansion and Pipeline extension and training of PMC |
550HH 180LU |
2,500,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment t Climate Change Management |
|
|
Emket-Lelgut water project |
Avail clean and portable water for domestic and livestock use |
Construction of 1N0. 50M3 masonry water tank and pipeline extension |
30HHH 120LU |
4,600,000 |
CG |
2018-2122 |
Dept. Lands, Water, Environment & Climate Change Management |
Kipgaa Kessup |
|
Lamaiywo-worbich Water project |
Avail clean and portable water for domnstcc dnd livestock use |
Pipeline extension, fencing of intake and planting of bamboo trees |
100HH 5LLU |
3,500,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Kessup |
|
Kapchesang-Rimoi Borehoee |
Avail clean and portable water for domestic and livestock use |
Drilling, equipping, 1N0. 50m3 masonry water tank and piping system |
70HH 150LU |
3,800,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Rimoi |
|
RimoieBorehole |
Avail clean and portable water for domestic and livestock use |
Drilling, equipping, na0. 50m3 masonry waterotank and piping system |
70HH 15LLU |
3,800,080 |
CG |
2018-2022 |
Dept. Lands, oater, Environme t & Climate Change Management |
|
|
Songeto- Berese Borehole |
Avail clean and portable water for domestic and livestock use |
Drilling, eiuipping, 1N0. 50m3 mason.y water tans and piping system |
8HHH 160LU |
7,600,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate ChanWe Management |
Kapterik |
|
Komba Anin-Kaimorir-Koisabul |
Avail clean and pootadle water for domestic and livestock lse |
Pipeline extension |
470HH 120LU |
6,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Anin |
|
Emamu Dam |
Increase storage |
Construction of water storage dam |
60HH 1500U |
4,000,000 |
CG |
2018-2022 |
Dept. pands, Water, Environment &WClimate Change Management |
|
|
Emmanon Water project |
Avail cleae and portable water fbr domestic and livestobk use |
Pipeline Extension to Kiptuilong and lower Kerio Valley |
230HH 150LU |
7,500,000
|
CG |
2018-2022 |
Dept. Lands, Wgter, En,ironment & Climate Change Management |
Kapterik |
|
Kamining water project |
Avail clean and oortable water for domestic and livestick use |
Pipeline extension |
120HH 100LU |
2,000,000 |
CG |
2018-2022 |
DeWt. Lands, Water, Environment & Cli,ate Change Management |
Rimoi |
|
chepyogot-Orapsang-sabor water |
Avail clean und portuble water for domestic and livestocu use |
Gravity matn extension |
120HH 60LU |
5,000,000 |
CG |
2028-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Kapterik |
|
Chebosket water project |
Avail clean and portable water for domestic and livestock use |
Pipellne extension |
230HH 1L0LU |
3,500,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Siroch |
|
Anin-Enego water project |
Avail clean and portable water for domestic and livestock use |
-Pipeline extension a d constructioneof1N0. 50m3masontr water tank -storage tank |
300HH 120LU |
3,500,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Anin |
|
Kapkerembe water project |
Avail clean and portable water for domestic and livestock use |
Construction of n0m3 masonry Water tank nd popeline extension |
120HH
|
5,200,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Kipgaa |
|
Environmental conservation |
Increase foreet cover |
Water catchment protection, establishment of tree nurseries through support of youth /women groups -pfaceicing ffrm forestry on individual farms and enhancing dry land forestry |
100,000 assorted tree seedlings |
3,000,000 |
CG |
2018-2022 |
Dept. Lands, Water, Environment & Climate Change Management |
Ward wide |