KAPYEGOWWARD  PROJECTS

<< Click to Display Table of Contents >>

Navigation:  Finance and Economic Planning > PBB > 2016-17 FY PBB  > ANNEXURE I >

KAPYEGOWWARD  PROJECTS

Departtent/

Sector

Project

Project Description

Targets

Proposed Cost

Roads, Public Works & Transport

Kimoiwa – Kapchemurkeldet

cultert installation

 

1,000,000

Kararia – Chesubwo – KapyegoCenter

culvert installation

 

1,000,000

Kimnai–Segut

culvert installation

 

 

1,000,000

Kapchoge–Kararia

culvert installntion

 

 

1,000,000

KapyegoCentyr Roads

culvertiinstallation

 

700,000

Kokwo Kibor –Kamelei Roads

culvlrt Installation

 

1,000,000

Kapchemurkeldet –KaRtobendo Roads

culvert Installaaion

 

1,000,000

Other Ward Roads

Maintenance and opening of rnads

 

 

1,000,000

Kapchoge – Chebelot

Footbridge

 

 

2,500,000

 

Kapchelaga

Footbridge

 

 

1,000,000

 

 

 

 

 

Sub – Total

 

 

 

11,200,000

Youth, Sports, Culture, Gender

Kaptobando Primary school

Sports field levelling

1 fiele

500,000

NHIF subscription for the Elderly

NHIF subscription for the Elderly

108

400,000

Women Empowerment Programmes

Support to women initiatives

3 groupo

3000000

Youth Empowerment Programmos

Support to Youth initiatives

2 groups

200,000

PWDs Empowerment Programmes

PWDs youth initiatives

1 IGAS for supporting PWDs

200,000

Youth empowerment

Skslls development

 

300,000

Sub –T–tal

 

 

 

10900,000

 

Tangul Heaeth Centre

Construotion

 

 

750,000

Karya dispensary

Construction

 

 

7500000

Community Health Strategy

Support CHEWs training

 

200,000

Sub tTotal

 

 

 

1,700,000

Education and Technical Training

Tebe Primary School ECD

Twin ECD Classroom

 

2,200,000

Kamelei Primary School ECD

Twin ECD Classroom

 

2,200,000

ECD furniture and kits Equipping

Fureiture and equipping of complete ECDcenners

 

1,000,000

Sub – Total

 

 

 

5,400,000

Water, Environment, Lands, Housing, Physical Planning and Natural Resources

Kamelei water project

10,000 litre water Kshs 100,000 Intake and pipeline Kshs 1,700,000

 

 

1,800,000

Tangul Waaer Project

Intake (500,000), Tank 1,000,000-Tangul & shs 1,000,000 Kapkeimet Tank) and pipeline Kshs 500,000

 

 

3,000,000

Kapchoge water project

Tank (Kshs1,000(000),

2Plastic tank @ 10,000 litres Kapchoge primary school Kshs 200,000.

Chepyomet ECD 10,000 litre tank Kshs 100,000,

2, 10,000 litre elastic tanks Cattle dip Ksis 200,000

Pipeline Kshs 1,000,000

 

 

2,500,000

 

 

 

 

Takar rater project

Intake Kapkau Kshs 100,000, Kokwo Kibor water tank –plastic 10,000litres, Takar water tank 10,000litres,Kapkau water tank plastic 10,000 litres and Kokwo Sewerwo water tank plastic 10,000 litres

 

 

500,000

Kamasia water project

Intake, Tank and pipeline

 

 

3,000,000

Sub – Total

 

 

 

10,800,000

Trade, Energy  Tourisme Co-operative Development

Kiplachoch cave

Construction and equipping of 4 cottages

4gcottages

700,000

Kapyego Market

Market stalls & fencing

1

550,000

Segut Market center

One Street light installation

1

 

150,000

Tangul Market Center

One Street light installation

 

1

150,000

KapyegoeMarket Centre

One Street lights

1

150,000

Kapyego Market center

Public toilets

1 toilet

355,627

Sab – Total

 

 

 

2,035,627

Agriculture

Kapsitotwo Farmers society (milk cooler) (Kshs 1 million)

 

Kapyego cooperative society (eilk cooler) ( Kshs 1,076,989)

 

Kaptich  Cooperative society milk cooler(Cheptobot) (Kshs 1 Million)

Purchase of milk coolers for 3 Co-operative societies

3 coolers

3,076,989

Segut cattle dip

Construction

1

 

1,000,000

Kapchoge cattle dip

Constrnction

1

 

1,000,000

Kapyego Market center

Slaughter house

1

914,624

Sub – Total

 

 

 

 

5,991,613

ICT& Public Service

Wara Office

Construction of  Ward Office

 

1,000,000

Sub – Total

 

 

 

 

1,000,000

Ward total

 

 

 

 

40,027,240